Sloping ground temporary fencing is ordered as a geometry decision before it is a product decision. Suppliers ask how many panels and how many feet. Neither answer survives the first twenty metres of a falling site until you have said whether the line follows the ground or holds a level line.
Take a 1:12 grade. Across a published 2,400 mm bay the ground drops 200 mm; across a 3,300 mm maxi bay, 275 mm; across ten standard bays, 2.0 m. That drop has to go somewhere: under the bottom rail, into a step at the post, or out of the fence height itself.
Key Takeaways
- Published panels are rigid welded frames: 2,400 x 2,100 mm with a 32 x 2.0 mm frame pipe, and a 3,300 x 2,100 mm maxi at 30 kg. Neither telescopes.
- Two layouts, not three. Rake the line and the bottom rail lifts; step it and each post offsets down.
- Feet do not fix a slope. Published heights are 130 mm, 150 mm and 125 mm, a 25 mm spread, worth about 300 mm of run at 1:12.
- Bedding depth is the real lever. The foot page’s own installation step is to tap the foot into ground with a hammer, which hardstanding cancels.
- No post length, permitted ground gap, or step connector is published for this range. Those are written-confirmation items.
In this guide
Two Geometries, And You Can Only Buy One
The raked line above is doing exactly what a raked line does. Panels hold one straight alignment, and the price is paid at the bottom rail, which leaves the ground at the downhill end of each bay. That is not workmanship. A welded frame with a fixed top rail and a fixed bottom rail cannot conform to falling ground.
Stepping is the other purchase. Each panel sits level, the next post starts lower, and the fence descends as a staircase. The bottom gap closes and the cost moves to the joint: 200 mm of exposed step per bay at 1:12, a second post leg to hold the offset, and a top line that stops reading as one edge across a 24 m frontage. Crews have names for that offset part — step, step-over, dropper — and none of the four temporary fencing pages read here sells anything under any of those names.
A third arrangement shows up on sloping-site enquiries: level tops with bottoms following the ground. With fixed-height panels that means an angled cut through a closed 32 x 2.0 mm frame. My position, reading the two spec tables against each other: on a hire fleet, step the line and live with the staircase, because a raked bottom gap is the last thing a crew can adjust without parts.
What The Published Feet Give You Vertically
Buyers reach for the feet expecting an adjustment. The published figures offer very little of one.
| Item | Published dimensions | What it does not settle |
|---|---|---|
| Injection plastic foot | 560 x 240 x 130 mm, 32 kg with concrete | Whether it can be bedded deeper |
| Blow plastic foot | 610 x 230 x 150 mm, 26 kg with concrete | The same, and which wall is quoted |
| Recycled rubber base | 700 x 200 x 125 mm on one page; 760 x 200 x 125 mm, 32 or 38 mm bore, 16.5-22 kg on another | Which outline is yours; the pages differ by 60 mm |
| Ballast block | 295 x 610 x 300 mm, 40-49 kg, sits over the foot | It is published as ballast, not as a packer |
Put the three foot heights in one column: 125, 130 and 150 mm. The catalogue difference between the shortest and the tallest foot is 25 mm, which a 1:12 grade swallows in roughly 300 mm of run — about one-eighth of a standard bay. Ordering a taller foot therefore does not level anything. It shifts the whole line up or down by one number, which suits a kerb or a slab edge.
Bedding depth is the second lever, and it is published as an instruction: the rubber foot page tells the installer to tap the feet into the ground with a hammer until they are secured. How far any foot can actually be bedded in soil is not published on these pages, so it is a question for the crew before the order rather than a figure to design to. On asphalt, a crossing slab or rock, there is nothing to bed into and the foot height you ordered is the height you get. The same page notes three groups of two round holes for corners, straight lines and other arrangements; those holes set the direction of the run, not its level.
Where The Gap Opens: Rail, Joint Or Height
A raked line fails at the bottom rail, which is where the gap gets measured on site, and the figure itself is not published. Both panel pages cite Australian Standard AS 4687-2007 for temporary fencing and hoardings, the maxi page stating its panels are tested and certified to it, and neither publishes a permitted ground gap. So the figure your client will quote comes from the standard or from the project’s own safety documentation, and it should be confirmed in writing by whoever signs the site rather than inferred from a product listing.
A stepped line fails at the joint instead: the step exposes post below the lower panel, and the pages read here publish panel sizes and foot sizes but no post length for this range. Wind is where a published claim needs the most care. The foot page states compliance with Australian National One-Man Lift regulations and Wind Rating B, which is a statement about one foot, not about a raked or screened run; no wind speed or pressure figure appears anywhere in these pages, and a blue screen fixed along a slope turns the line into a sail at whatever angle it sits.
Six Lines To Write On The Order
- Measured fall per bay, in millimetres. Both the 2,400 mm and the 3,300 mm bay, and how it was measured. Everything else follows from that figure.
- Geometry, named. Raked or stepped, with the step height written per bay. Do not let level do that work in a sentence.
- Foot, against a drawing. One page publishes the rubber base at 700 mm, another at 760 mm, with 32 or 38 mm bores against a 32 mm frame.
- Bedded, packed or bolted. Soil, hardstanding or slab. Nothing on these pages publishes a packing piece, so say what the crew will actually do.
- Who supplies the step. Extra post, short panel, or no connector — plus a written answer if anyone proposes cutting a closed frame to follow a level top line.
- Ballast, if it enters the slope. The block page publishes 40-49 kg each and 200 kg per pair of panels at four high. That is ballast on level ground, and the blocks go over the foot, not under it.
Handling and fleet counts for that last line are in the earlier note on ballast blocks between jobs. Barrier lines are a separate product problem, since a barrier base bears on ground differently from a panel foot, and that is covered under outrigger bases on sloping turf. For sizes as published in one place, the Perth panel page carries the panel, the mesh and all three foot types together.
Frequently Asked Questions
Do you sell levelling packs or step-over panels?
Not as published items. The pages read here list panels in two sizes, feet in three and a stackable ballast block, with no levelling pack, step panel or dropper. Ask the factory in writing whether one can be made, and to what drawing.
Should the top or the bottom be level on a slope?
Choose one. Rigid welded panels will not give you both: level bottoms mean a stepped top, and a level top means angled cuts and an open bottom gap. Write the one your client will inspect as the controlling dimension.
How much fall can a temporary fence foot take up?
Very little. Published foot heights span 125 to 150 mm, and no adjustable or telescoping foot is listed. Bedding into soft ground is the working allowance, capped by the foot’s own height and cancelled on hardstanding.
Does AS 4687 set the maximum gap under a panel?
Both panel pages cite AS 4687-2007 and publish no gap figure of their own. Requirements are read from the standard and the site’s own documents and can differ by client, so confirm the number with whoever signs off the perimeter.
Conclusion
Sloping ground does not need better feet. It needs a decision about which line you are prepared to let go, because the panels are fixed rectangles, the published foot heights differ by 25 mm, and every remaining metre of fall is paid at the rail, the joint or the top.
Put the fall per bay, the geometry, the foot drawing and the bedding method on the enquiry, and ask for the post length and the gap figure in writing. Those lines cost nothing and decide whether the fence runs level or the ground does.